Footing Foundation Begins – PCC & Column Marking Completed May-25-2025

Work done on: Sunday, 25th May 2025

Even on a Sunday, the energy at the site was high!Day before Yesterday, we achieved a key construction milestone by completing:

1. Plain Cement Concrete (PCC) for all footing pits

2. Footing column marking for structural alignment

This sets a strong and precise base as we gear up for reinforcement and footing concrete.

Site Conditions on Sunday:
- Weather: Pleasantly cool at 24°C, partly cloudy and rainy 
- Cement Used: Bharthi Ultrafast – consistent and ultra fast setting 


Work Quality: On point, with good finishing across all pits

I'm thrilled to see things taking shap brick by brick. Stay tuned for the next phase as we prep for reinforcement and concrete casting