Staircase, Lintel & Upcoming First Floor Work
We are currently in the “Column rising and blockwork up to lintel level for the ground floor” phase, scheduled from 21st June to 5th July 2025. The stage is currently completion, with steady progress across key activities.
🏗️ Progress:
•Staircase & Lintel Shuttering.
•Blockwork Base Course.
•Blockwork up to Lintel Level.
•Centering Work - Sunday Holiday (Today)
Resume on Monday: Activities will pick up from Monday with preparations for lintel casting
Upcoming Activities:
•Lintel Casting – Targeted for completion by next week First Floor Moulding Work – Planned to begin right after lintel casting
✨ On-Site Optimization: Entrance Height Adjustment:
The original design had a 6-feet entrance height due to the staircase landing. However, based on a practical recommendation from the head mason (Dhananjay) and site engineer’s review (Uday and Prashant), we increased it to a 7-foot clearance. This eliminates headroom issues and allows smoother access, demonstrating the proactive ownership and care taken by every stakeholder involved in the project.
📸 Progress videos – Coming Soon!
We'll be uploading pictures of the completed shuttering, staircase formwork, and more to document the ongoing work.