๐Ÿ—️ RMC Footing Pour Completed JUN-1-2025

๐Ÿ“ Location: Site – Footing Area
๐Ÿ‘ท Activity: Ready-Mix Concrete (RMC) Footing Pour
 ๐Ÿ•’ Time: 3:00 PM – 5:00 PM
☁️ Weather: Clear and ideal for concrete work

 ✅ Work Summary:

The RMC footing pour was successfully executed today as planned. Key highlights include:
- Two large RMC trucks arrived on-site with timely coordination.
- The footing pour proceeded smoothly under favorable weather conditions.
-The following team members were present and oversaw the activity:

1. Prashanth – Site Engineer, B&B
2.Uday–  Site Engineer , HomehSquadz
3.Dhananjay Head Mason – Site coordination
4.Anil Contractor - HomehSquadz proprietor 
5.RMC Vendor Team – Responsible for pour execution and sample collection

 ๐Ÿงช Quality Assurance:
Standard quality protocols were followed on-site:
Slump Cone Test was performed to verify concrete workability.

Cube Test:
  -Cubes were filled from the RMC sample  batch.
 -Dampers were placed appropriately on-site for curing.
  -Reports will be submitted by the vendor as per process.

Post-Pour Vibrator Usage and Leveling:
- Concrete was compacted using a mechanical vibrator to eliminate air gaps.
- Surface leveling was completed immediately after to ensure structural integrity and finish quality.

๐Ÿ“ธ Visual Highlights:
>  RMC truck arrival
> Pour in progress
> Cube sampling and cone 
> Supervision team on-site
๐Ÿ“ Notes:

1.No issues reported during pour.
2.Ideal weather and early prep ensured smooth execution.
3.Awaiting vendor QA reports (cube test results) as per timeline.

Comments

Popular posts from this blog

The Future of Home Design is Here - GenAI Elevation Visualization

Choosing the Right Sump Tank Size for My Home – A Thoughtful Decision

All Set for External Plastering!