Third Floor Mould Done – September 20, 2025
We’ve crossed another milestone in our construction journey! On 20th September 2025, the moulding work for the third floor has been successfully completed. With this, the main shell up to the third floor is now in place, and the structure is steadily rising skyward.
Right after finishing the moulding works, we successfully completed the concrete pour for the third floor slab and beams on 20th September 2025.
Right after finishing the moulding works, we successfully completed the concrete pour for the third floor slab and beams on 20th September 2025.
Next Steps
Curing has already begun — continuous water curing is being done to keep the slab moist.
The formwork will remain in place until the concrete gains sufficient strength.
After curing, we’ll proceed to brickwork and walls for the oth water tank room and pf wall.