Column Work & Brick Masonry (June 20 - 23)
Following up on our 19th June update, where we’re happy to share further progress at the site.
Curing is being carried out diligently using 1HP Sharp water pump, ensuring uniform hydration across all vertical elements.
Column Work and Curing:
The column and Floor PPC concreting was completed on 21st June as per ahead of B&B schedule(approximately by month).
On average, curing is being done 4 times a day to maintain proper moisture levels and avoid surface cracks.
M25 grade concrete was used for column casting with a 0.5 water-cement ratio to ensure durability and structural strength
Brick Masonry Begins
Today, first-level brick masonry work has been completed above the plinth beam.
Concrete Blocks are being used to ensure uniformity and strength.
Mortar mix used: 1:6 ratio (cement:sand), complying with standard construction norms.
Vertical and horizontal joints are being aligned and thickness maintained as per design specs (10 mm).
QA Checks & Approval Awaited
We’re currently awaiting quality checks and B&B site engineer Prashanth’s approval before moving to the next level.
Internal alignment, plumbing rough-ins, and electrical conduit provisions are under verification.
We’ll keep updating as we progress with lintel casting and subsequent levels.
📌 Stay tuned for the next update where we cover beam shuttering and slab preparation