Staircase, Lintel & Upcoming First Floor Work
We are currently in the “ Column rising and blockwork up to lintel level for the ground floor ” phase, scheduled from 21st June to 5th July 2025. The stage is currently completion, with steady progress across key activities. 🏗️ Progress: •Staircase & Lintel Shuttering. •Blockwork Base Course. •Blockwork up to Lintel Level. •Centering Work - Sunday Holiday (Today) Resume on Monday: Activities will pick up from Monday with preparations for lintel casting Upcoming Activities: •Lintel Casting – Targeted for completion by next week First Floor Moulding Work – Planned to begin right after lintel casting ✨ On-Site Optimization: Entrance Height Adjustment: The original design had a 6-feet entrance height due to the staircase landing. However, based on a practical recommendation from the head mason ( Dhananjay ) and site engineer’s review ( Uday and Prashant ), we increased it to a 7-foot clearance. This eliminates headroom issues a...